Weather Strip -- North971 viewsThe weather strip (or brush) on the long side of the roof.
|
|
Weather Strip -- West905 viewsWeather stripping on the west side. The roof moves to the west.
|
|
Panorama to East1037 viewsA panoramic view showing the nice lack of pump equipment in the foreground.
|
|
View to Warm Room887 viewsInterior paint is complete, looking toward the warm room.
|
|
Almost Done -- View to South883 viewsJust about ready for the final inspection.
|
|
View to South817 viewsA view to the south with better color balance than the one posted a couple of weeks ago.
|
|
View to Warm Room932 viewsA composite view (note the stitching errors) looking from the observatory into the warm room.
|
|
Southeast Corner977 viewsPaint is mostly complete and the bottom trim on the wall is partially complete.
|
|
Stucco Complete View to East946 viewsThis view to the east shows the contrast of color between the walls and the roof.
|
|
Stucco Complete View to South832 viewsThe stucco is complete and the column installed in this view looking south.
|
|
Wide View to East921 viewsWith the roof on the observatory is looking pretty good.
|
|
Roof Complete View South875 viewsRoof on and base stucco complete, looking to the south.
|
|
|